The windfarm construction site is located on the A726, one kilometre south of East Kilbride. Deliveries are scheduled to start on 18 April, continuing through to the end of May. Live updates on the deliveries will be provided here and on the CleanEarth LinkedIn page.
For any queries or concerns, please email Rigmuir.Transport@cleanearthenergy.com or call 01208 895576. For urgent queries during the delivery window please call 01208 640285.
There are no scheduled road closures.
The following deliveries are currently scheduled:
Monday 29 April between 2am and 6am (wind dependent)
Wednesday 1 May between 2am and 6am (wind dependent)
Friday 3 May between 2am and 6am (wind dependent)
Route
Below is the planned route of travel for all components.
Full route from King George V Dock to the windfarm site:
Blantyre and Hamilton section of the route:
East Kilbride section of the route:
Blade component deliveries will take place overnight. Nacelles and towers will travel during off-peak hours. All deliveries are dependent on suitable weather conditions. Updates on deliveries will be shared on this page, but for more immediate updates please visit the CleanEarth LinkedIn page.